Soft Landings is a way of running a fitout so that the project does not end when the builder hands over the keys. The design team and contractor stay involved from the first brief through move-in and into the first months of occupied use, so the space your staff walk into is the space you asked for. For an Australian business, that means a fitout judged by how the office works in practice, not by whether it was finished on the day.
That is also how we think about workplace projects at Niche Projects: strategy, design and construction are one connected job, and the brief is only proven when people are working in the space. This guide explains the Soft Landings approach in plain terms, sets out its stages, shows who needs to be involved and gives you a routine you can apply to your next fitout or refurbishment.
TL;DR
- Soft Landings is a structured process that links the brief, design, handover and aftercare, so a fitout is tested against real use after move-in.
- The Australian and New Zealand framework runs from inception and briefing through design review, pre-handover, initial aftercare and one to three years of extended aftercare and post-occupancy evaluation.
- Fitouts are where the process is most often skipped, usually because of cost, time pressure or a belief that it only suits large buildings.
- A post-occupancy review three to six months after completion, using surveys or interviews, is a practical way to check the fitout delivered what the brief promised.
- You get the most from it by writing measurable goals into the brief and agreeing who is responsible for aftercare before construction starts.
Table of Contents
- What Soft Landings means in an office fitout
- The stages, from brief to years of aftercare
- Why the aftercare matters: evidence from an occupied building
- Who needs to be involved
- How to check the fitout delivered: the post-occupancy review
- Soft Landings and an inclusive, productive workplace
- Building Soft Landings into your next fitout
- How Niche Projects fits in
- FAQ
- Sources
What Soft Landings means in an office fitout
Most fitouts follow a familiar line: brief, design, build, handover, then everyone moves on. The building contractor finishes defects, the designer files the drawings and the business is left to make the space work. Problems that only appear under real occupancy, such as a meeting room that is too loud, air-conditioning that does not suit a zone or a layout nobody uses the way it was drawn, become the tenant’s problem.
Soft Landings closes that gap. The idea comes from the building services industry in the UK, and the Australian and New Zealand framework published by CIBSE in August 2014 adapts it to local construction practice, covering the project from inception through to operation. CIBSE is the professional body for building services engineers, and the framework was shaped through seminars with architects, services consultants, contractors, owners, agents, occupiers and operations managers.
For fitouts specifically, BSRIA (the UK building services research body) published a 2022 guide on Soft Landings for fit-outs. It notes that the process is often overlooked in fitout projects because of financial or time constraints, or a misunderstanding of how relevant it is. In other words, a tenant fitting out a floor is just as entitled to a smooth landing as the owner of a new tower.
A useful way to put it: Soft Landings treats the fitout as a promise about how your people will work, and then checks that the promise was kept.

The stages, from brief to years of aftercare
The CIBSE ANZ framework lists five stages. Here is what each one means for a tenant commissioning an office fitout.
| Stage | What happens | What it means for your fitout |
|---|---|---|
| Inception and briefing | Goals are set and agreed | You define how the office should perform, not just how it should look |
| Design development and review | Design is tested against the brief | Layouts, services and finishes are checked for how they will be used |
| Pre-handover | Preparation for occupation | Staff briefings, building controls and systems are explained before move-in |
| Initial aftercare | Support in the first weeks of use | Someone is on hand to fix teething problems fast |
| Years 1 to 3 | Extended aftercare and post-occupancy evaluation | The space is reviewed and tuned against the original goals |
The 2017 FIS guide to office fit-out and refurbishment, from the UK’s finishes and interiors sector body, gives a feel for the commitment: the contractor may stay available on site for four to six weeks after handover and remain contactable for at least a year, potentially up to three. It also describes a project review no earlier than one year after occupancy. These are UK figures, and the right commitment for your project depends on its size, so treat them as a reference point when you set expectations with your project team.
Stage 1: Inception and briefing
This is where most of the value is created. A brief that says “modern, collaborative, 120 people” gives nobody anything to be held to. A brief written for Soft Landings states outcomes you can check later:
- How many people will be in the office on a typical Tuesday, and how many on the busiest day?
- What proportion of the day will staff spend in focus work, in meetings and in collaboration?
- Which accessibility and inclusion needs must the space meet from the first day?
- What comfort, noise and air quality expectations do you have?
- What would you want to see in a staff survey six months in for you to call the fitout a success?
This is the point at which workplace strategy earns its keep. Understanding how your teams actually work, before anyone draws a floor plan, produces a brief that can be tested. Our guide to workplace strategy: definition, inputs and how it works sets out what goes into that thinking.
Stage 2: Design development and review
Once a design exists, it is reviewed against the brief, not only against the budget. Does the number of focus rooms match the focus work you described? Is the layout accessible for everyone you listed? Do the air-conditioning zones match where people will actually sit? Our article on office design and air-conditioning explains why services and layout have to be planned together.
This stage is also where procurement decisions lock in long-lead items such as joinery, furniture and glazing. Keeping orders, approvals and revisions organised matters here, and a clear process, like the one described in streamlining purchase orders for designers, keeps what was approved in design identical to what arrives on site.
Stage 3: Pre-handover
Before move-in, the people who will run and use the space need to understand it. That includes how the lighting controls work, how meeting rooms are meant to be booked and used, and who to call when something is not right. A walk-through for the office manager and a short briefing for staff turn a handover from a key exchange into an introduction.
Stage 4: Initial aftercare
The first weeks are when the unexpected shows up. Aftercare means a named person on the project side is available, issues are logged in one place and fixes happen quickly. Staff who see a problem solved in days form a very different view of the new office from staff who are told to submit a request.
Stage 5: Extended aftercare and post-occupancy evaluation
This is the stage that separates Soft Landings from a normal defects period. You measure how the space is performing against the brief and adjust. The next section covers how.
Why the aftercare matters: evidence from an occupied building
An Australian example shows why tuning after move-in is not a luxury. The SBEnrc industry report published in April 2019 followed a Melbourne office building where monitoring-and-tuning meetings were held every two months. The group included the sustainability design team, main contractor, facilities manager, mechanical and electrical service contractors, the building management system contractor and an independent commissioning agent.
The report found that intervention strategies gradually narrowed the gap between expected and actual building energy performance from July to December 2018, and that a later override on an air-conditioning pump widened it again. The lesson for any tenant is simple: how a space performs depends on day-to-day decisions by people, so monitoring and follow-through have to continue after commissioning.
The FIS guide takes the same view from a fitout angle, describing Soft Landings as a way to reduce the gap between expected and actual performance. Move-in is the start of evaluation and adjustment, not the end of the job.
Who needs to be involved
Soft Landings only works if responsibility is clear. In a tenancy fitout the cast is smaller than in the Melbourne building above, but the roles are the same:
- The business owner or executive sponsor: signs off the outcomes in the brief and keeps them in view when budget pressure hits.
- The office manager or facilities lead: becomes the day-to-day contact for aftercare and the person who learns how the space is meant to run.
- HR or people and culture: owns the staff experience measures, including inclusion and accessibility feedback.
- The designer and workplace strategist: carry the brief through design review and take part in post-occupancy evaluation.
- The builder or construction manager: stays contactable after handover and fixes what the review turns up.
- Building services contractors: for air-conditioning, fire, electrical and controls, they are the ones who can tune systems once real occupancy patterns are visible.
The common failure is that each of these parties is engaged only for their own phase. Having one team that handles strategy, design and construction management shortens the chain of handovers, and that is the reason we run these services together. If you are a construction lead, the same principle applies on the delivery side: a single point of accountability from design to aftercare removes the argument over whose problem a post-move-in issue is.
How to check the fitout delivered: the post-occupancy review
The Queensland Government’s guideline on post-occupancy review, last updated on 9 July 2025, defines it as measuring whether occupants’ needs were satisfied and how well the design, construction and occupancy process worked. It is written for government agencies, but the method suits any business. It recommends carrying out the review three to six months after completion, once people have settled in.
Here is a routine drawn from that guidance.
- Go back to the brief. List the outcomes you set at inception. Each one becomes something to check.
- Gather views from staff. The guideline suggests interviews, discussion groups or structured surveys. A short survey covering comfort, noise, finding a place to work, meeting room availability and accessibility is enough for most offices.
- Record and analyse by category. Group results by theme (acoustics, temperature, layout, technology) so patterns are visible, not buried in comments.
- Add technical checks where useful. Temperature, air quality, lighting and noise readings can confirm or explain what people report.
- Share the findings. Results go back to occupants and the project team, which shows staff their input mattered.
- Fix, then follow up. For major projects or a significant change in how people work, the guidance also points to follow-up reviews of productivity and other business outcomes.
A realistic worked example: a 90-person professional services firm moves to a new floor with a brief that promised enough quiet space for focus work. At month four, the survey shows staff in one zone rate noise poorly. The team checks the layout, finds an open collaboration area next to the focus desks and agrees an acoustic treatment and a change to the booking rules for that area. Without the review, the complaint would have lived on as grumbling at the kitchen bench.
Soft Landings and an inclusive, productive workplace
The Queensland guidance describes occupant reviews as an inclusive process, one that gives every kind of worker a say and can assess how well the workplace functions. That matters if you are an HR manager responsible for inclusion: a fitout that looked accessible in the drawings can still fail someone in practice, and a structured review is where you find out.
It also matters for space efficiency. A review that shows which settings are crowded and which sit empty tells you whether the floor plan matches how your teams really work. A recent Australian example is Cromwell’s May 2025 account of its own office transformation, where the brief called for a comfortable, inclusive and functional workplace with accessibility and room to grow. The finished space used collaboration areas, focus rooms, a library, wellness rooms and a multifaith room to cater for different work styles and needs. The principle carries over to any organisation: varied settings, defined up front and checked after move-in.

For more on designing the physical space, see our articles on designing an accessible and inclusive office, ergonomic office design and prioritising workplace wellness in your fit-out.
Building Soft Landings into your next fitout
You do not need a large building or a big budget to apply the approach. You need decisions made early and written down. Use this checklist when you brief and appoint your team.
- Write measurable outcomes into the brief. Occupancy levels, noise expectations, accessibility requirements and a target survey result.
- Name the aftercare lead on each side. One person for the business, one for the project team.
- Agree the aftercare period before construction. Say how long the builder and designer stay contactable and how issues are logged.
- Schedule the review dates in the program. Put the post-occupancy review in the calendar for three to six months after completion and a later one for year one.
- Plan the staff briefing. Treat move-in communication as part of the project, not an afterthought.
- Keep the sponsor involved. Fitouts drift when nobody senior holds the outcomes.
Timing and disruption also deserve a place in your plan. Our guide to managing your office fit-out covers the practical side of running a project while the business keeps trading, and designing for agility helps you leave room for change so a layout that suits you now still works as the team grows.
How Niche Projects fits in
A Soft Landings style fitout depends on continuity between the people who plan the workplace, those who design it and those who build it. Niche Projects combines workplace strategy, creative design and construction expertise for commercial clients across Sydney, and our delivery approach is built around consistent communication with the client. If you are planning a move or a refresh, our Sydney office fitout and refurbishment service is the place to start, and our Sydney office design page covers the design side. Tell us the outcomes you want your workplace to deliver, and we will build the project around them.
FAQ
Is Soft Landings only for large buildings?
No. BSRIA’s guidance exists specifically for fitouts, and it notes the process is often overlooked there because of cost, time or a belief that it does not apply. The scale of the aftercare can match the project: a modest tenancy might need a named contact, a staff survey and one review meeting.
How long does Soft Landings aftercare last?
The CIBSE ANZ framework includes initial aftercare followed by extended aftercare and post-occupancy evaluation across years one to three. The UK FIS guide mentions a contractor being on site for four to six weeks and contactable for at least a year. Agree the period for your own project in the contract before work begins.
When should we run a post-occupancy review?
Queensland Government guidance recommends three to six months after completion, so occupants have had time to settle in. Many organisations then follow up later, for example at around one year, to check that fixes worked and to look at business outcomes such as productivity.
Who should be on the Soft Landings team for a tenancy fitout?
At minimum, an executive sponsor, the office or facilities manager, someone from HR, the designer or workplace strategist and the builder. Add services contractors for air-conditioning, fire and controls where those systems are part of the project.
Sources
- Soft Landings Framework, Australia and New Zealand (CIBSE, August 2014)
- Soft Landings for Fit-Outs, BG 81/2022 (BSRIA)
- Office fit-out and refurbishment guide (FIS, 2017)
- SBEnrc industry report on a Melbourne office building case study (April 2019)
- Post-occupancy review guideline (Queensland Government, updated 9 July 2025)
- An inside look: Transforming office spaces (Cromwell, May 2025)